Road and utility survey, as-built plan: surveying the street before and after the works

A connection, a road resurfacing, a sewer network: design offices and municipalities need to know the street as it is, with its kerbs, manholes and gradients. And at the end of the works, the project owner must know what has actually been built. These are two different surveys.

Updated on 24/10/2026

Street with utilities, street furniture and surveyed points
Street with utilities, street furniture and surveyed points

Your situation

  • A design office is preparing a road, sewerage or drinking water study.
  • A municipality is planning the resurfacing of a street or a junction.
  • A subdivision or utility works site is ending and the project owner must receive its as-built records.

For a building plot, the appropriate document is the topographic plan of the plot. This guide deals with the public space: the street, its structures and its utilities.

Before the works: the road and utility survey

The survey, tied to the Lambert Morocco system (Merchich datum) and to the NGM (Morocco's national levelling datum), shows:

  • the occupation boundaries along the street line, kerbs, pavements, verges and traffic islands;
  • the visible utility structures: manholes and covers, valve boxes, fire hydrants, telecommunication chambers, poles, cabinets and street lights;
  • signage, steps, walls and roadside trees;
  • carriageway profiles about every 30 m, at each change of gradient and at each intersection;
  • the cover and invert levels of the stormwater and wastewater networks, essential for computing the flow gradients.
Road survey: adjoining buildings, spot heights, contour lines, manholes, street lights and gullies (example, fictitious data)
Road survey: adjoining buildings, spot heights, contour lines, manholes, street lights and gullies (example, fictitious data)

After the works: the as-built plan

Under ONIGT Standard 08 (ONIGT: National Order of Surveying Engineers), the as-built plan describes the works actually carried out at the end of construction, comparing them with the project design plan. Starting from the authorised plan or the design plan supplied in digital format (DXF), the surveying engineer (IGT) surveys:

  • the final state of all the project's structures: utilities, roads, built volumes;
  • the boundaries of the existing roads and their rights-of-way;
  • the discrepancies with the project: setbacks, encroachments between the project footprint and the roads as built.
Laser scanner set up on the carriageway during a street survey
Laser scanner set up on the carriageway during a street survey

What a survey does not show

The measurements cover the visible parts of the structures. Buried pipes are not “seen” by a topographic survey: their route is shown for information only, with a separate legend, unless the IGT followed their laying (setting-out and survey before backfilling). The designation of the structures on the plan is not an opinion on their compliance.

What you receive

  • the plan at 1/200, 1/500 or 1/1000 in DWG and PDF, with its legend;
  • the table of cover and invert levels, and the requested profiles;
  • for an as-built survey, the discrepancies with the design plan highlighted.

Frequently asked questions

Does the survey locate buried utilities?

No. It records the visible structures (manholes, gullies, chambers); the buried route is indicative, unless the laying was followed.

What is the difference between a road survey and an as-built plan?

The first describes the street before a project; the second describes, at the end of the works, what was actually built compared with the project.

Can the design office use the plan directly?

Yes: it is delivered in DWG, in Lambert coordinates and NGM heights, with the utility levels.