When is it needed
- Earthworks interim statements on a site.
- Stockpile inventory.
- Capacity of a basin or a reservoir.
- Fill of a platform.
Our work
- Initial survey. Natural ground or reference state.
- Successive surveys. On the ground or by drone depending on the area.
- Computation. DTM (digital terrain model) difference and cross-sections: two methods that check each other.
Examples of assignments
- Monthly earthworks statements
- Aggregate stockpile
- Irrigation basin
- Industrial platform
What you receive
- Initial and final topographic plans
- Cross-sections
- Volume summary sheet
Reference framework
- ONIGT (National Order of Surveying Engineers) Standard 03
- ONIGT Standard 12 (volume computation)
Where we work
Based in Casablanca (Aïn Sebaâ), the firm carries out this service throughout Morocco: Greater Casablanca, Rabat-Salé-Témara, Fès, Tangier, Agadir, the Oriental and the South. Its survey crews travel to the site for the duration of the assignment.
Projects of the firm
- Topographic control of earthworksTopographic control of the earthworks of a major facility: survey crew on site, checks and regular reports.
- Industrial building setting-out and monitoringInitial and final topographic plans, setting-out of axes and steel frame, and earthworks volumes for a building.
Survey and capacity calculation of a basinAccurate topographic survey of a basin and calculation of its capacity to assess its sizing: method and deliverables.
Frequently asked questions
Why two methods?
They are independent: a discrepancy reveals a survey or model error.